Friday, October 1, 2010

Why mangers overrun time and budget



You might have heard that mangers often run out of time and budget. It is not that they don’t know how to manage or they lack skills. It is often the uncertainty which comes in the way of the project being undertaken. 

Some major mind storming decisions to be taken are -
  1. Ask a question to yourself – how much time it takes you to go home from your office. The answer you will give is a standardized one, say 20 minutes. Consider the following scenarios –
    • You get a traffic jam way back home,
    • You get a flat tire,
    • It was a hot weather and you didn’t got any traffic
    • You met an old friend and went to CCD or Barista
In such cases the time could range between 10 minutes to 30 minutes, or probably an hour. So, what you answered is correct, but a general one. If a Project manager answers this way and takes a project, then he would be able to complete the project with the grace of God!! The point is you need to keep some safety in between. How much safety is required?

    2.   Every project has a start date and an end date and there is one critical path (which takes the maximum   time to complete). Now it is the call of the manager, when to start the remaining tasks? If all the tasks are started simultaneously in the beginning then the manager would lose focus, and if all the tasks are started later i.e. at the completion of slack time, every task would become critical and delay in one task would increase the scheduled time and above all the manager would lose control over the project. 

Let us first understand what actually a project is. A project in simple term is a non-routine, complex task to be undertaken which is to be completed within a given time frame, resources, and budget; with the desired quality. It has a start date and an end date.
A project is not only confined to IT industry, it is viable for every service industry as well as manufacturing industry. There are some loopholes in every organization, due to which the problem of overrun occurs. 5 such reasons are listed below –
  1. Student’s syndrome - Students take a week’s time to complete their work which can be completed in 2 days, and still fail to complete it. The 5 extra days here is the safety they have introduced.
  2. Hierarchy of the Organization - The more the depth (no. of levels) of the hierarchy, more will be the safety (in terms of time) introduced at every level.
  3. Ambiguous Scope - Many a times the scope, i.e. the base-lining the project is not done properly. As a result a clear picture as to what needs to be done is missing.
  4. Dependencies - There can be many inter-links or relations between the tasks, which restricts the other tasks to start or complete without them.
  5. Multi-tasking – Manager can plan many things to be done in parallel. Suppose project A and project B are to completed and they are being carried in parallel. Say A takes 20 days to complete and B takes 25 days to complete. If after every 5 days the manager works interchangeably, then Project A will be completed in 35 days and Project B will be completed in 45 days. So, multi-tasking has its own pros and cons.
 To eliminate these loop holes we should follow the following standard steps as described in the book – “The Critical Chain”- by Eliyahu M. Goldratt –
  1. IDENTIFY – First identify the constraints or the areas which needs special attention
  2. EXPLOIT – Try to eliminate and mitigate them as much as possible
  3. SUBORDINATE – Find the substitutes available for the critical task to avoid delays
  4. ELEVATE – If the task require more resources (labour, equipment, machine, etc…), then deploy them
  5. ANALYZE – Check the system again for these critical tasks and follow the above steps again in order to solve the issue
Apart from these steps, a few more things could be done to improve the working efficiency and completing the projects before the due-date.  The following steps could be considered in some of the areas –
  1. No fixed time - Often we tell the workers to complete the task in x no. of days. So the worker works at that pace and works slowly so that the work is not completed before time. Instead of fixing time, try to make them understand that the project needs to be completed as soon as possible and is critical. Then they would work at their actual pace and the task would be completed well before it is scheduled.
  2. Negotiation - Try and negotiate with the local vendors on the time in which they could supply the raw materials or semi-finished goods or services.
  3. Reward for early completion - Give rewards to the vendor for early delivery of goods. State the reward in the tender for early completion along with the penalty for delaying the completion of the contract.
"Smart people learn from their mistakes, while wise people learn from others' mistake".
I hope this blog describes some of the major problems faced and some measures taken by the managers to curb them. Please add more insights to add value to this discussion on Project Management.  

6 comments:

  1. Very good initiative Robin! Well-structured, well-thought and nicely articulated.

    Now keep writing at least one article per week.

    ReplyDelete
  2. Thank You Sir
    I will try to be persistent in writing blogs.

    ReplyDelete
  3. Robin,

    You have been one of the most frequent visitors to my blog and I am happy to return the favor :-) Good observations.

    I hope from time to time you will illustrate your ideas with a careful case study or two.

    Thanks,
    Manas Fuloria

    ReplyDelete
  4. @ Manas Sir: Sure Sir, I will..

    ReplyDelete
  5. Great attempt!

    Many points are resembling what Ritesh sir teaches us. Nice way to express your ideas.

    Keep it up & Keep blogging!
    :-)

    ReplyDelete
  6. Hii,

    First of all Congratulation Robin for making debut in this world of learning.

    About the blog: Blog is very informative and explicable. Even I registered your starting example in my memory.

    My Input: Life is like series of projects which we need to accomplish in a required frame of time because we know best what Murphy's Law stats. So we need to remove buffer and slack time from our deadlines to grow as a born manager and leader and become successful in every part of life.

    Thanks for writing this blog.

    ReplyDelete